September 2013
Road transport from Manufacturer up to Porto Marghera, loading and ocean transport up to Paranagua (Brazil) of 1 Steam Drum measuring 19 x 3.5 x 4.5 and weighting 201 tons – UFN III Plant Project (Petrobras).
Read more…Road transport from Manufacturer up to Porto Marghera, loading and ocean transport up to Paranagua (Brazil) of 1 Steam Drum measuring 19 x 3.5 x 4.5 and weighting 201 tons – UFN III Plant Project (Petrobras).
Read more…Road transport from Manufacturer up to Porto Marghera, loading onto gearless coastal vessel, lashing / securing / dunnaging / welding, sea transport up to Le Havre (France), unloading and delivery up to final job site of 2 sets of Boilers (ttl 560 tons / 3,500 cbm) – EDF Project.
Read more…Road transport from Manufacturer up to Marina di Carrara port, loading onto Russian sea-river vessel and lashing / securing / dunnaging / welding (including supply of suitable grillage for weight spreading purposes) of 3 Reactors measuring 25.6 x 4.4 x 5 meters each and weighting 206 tons each -...
Read more…2 HRSGs and 2 Boilers (ttl 4,800 tons / 24,600 cbm) shipped in 3 lots from Porto Marghera to Rio de Janeiro (Brazil) – COMPERJ Project.
Read more…